Skip to main content

πŸ”‹ Batteries

Connecting a storage battery to Fuzz makes it possible to follow its state of charge and to control it: charge it with solar surplus, discharge it to limit the draw from the grid, or follow a grid exchange setpoint. This page covers the connection; the full form and the strategies are described in Add and control a battery.

βœ… Prerequisites​

ItemRequired
AssetA battery from the compatible list, using Modbus TCP, Modbus RTU or MQTT
Hosting modeModbus: Edge or Hybrid. MQTT: all modes
RoleAdministrator or Operator of the site
Battery settingModbus enabled, and remote power control allowed in the battery management system (otherwise Fuzz can only measure it)

πŸ“ˆ What Fuzz measures and controls on a battery​

Measurements: depending on the model, Fuzz reads the charge or discharge power, the current per phase, the state of charge (SoC, in %), the state of health (SoH) and the capacity. They appear in Assets (Batteries filter), in the Energy flow diagram of the site Overview page (BATTERY) and can trigger alerts (see Create and manage alert definitions).

Control: with the Set power action ticked (ticked by default at creation), Fuzz sends the battery a charge or discharge power setpoint. The setpoint follows the chosen strategy.

The strategies offered in Default Production strategy are Grid Exchange Target (default: the battery charges or discharges to hold the target grid exchange), Maximum Consumption (charges at maximum) and Maximum Production (discharges at maximum). Their detailed behaviour is in Add and control a battery.

Choosing the strategy according to the objective is explained in Control a battery according to an objective. If Set power is unticked, the battery is only measured.


πŸ–₯️ Declare the battery in the Console​

The form has seven steps: Battery parameters, Strategy parameters, Battery protocol, Phase mapping, Console, Metrics, Monitoring. The fields specific to the connection:

FieldMeaningDefault
Battery nameName, unique on the siteβ€”
Switchboard, MeterConnection switchboard; dedicated meter only if the battery does not provide its own measurementsβ€”
Maximum consumption current (A)Maximum charge current per phase. The Console shows the matching power: current Γ— 690 (16 A = 11.04 kW)16
Maximum discharge current (A)Maximum discharge current per phase16
Total capacity (kWh)Usable capacity of the batteryβ€”
Maximum State of Charge (%)Fuzz does not charge above this95
High State of Charge (%)"Well-charged battery" threshold80
Low State of Charge (%)"Low battery" threshold20
Minimum State of Charge (%)Fuzz does not discharge below this10
ProtocolModbus or Mqtt, then ModelModbus
Supported actionsSet powerTicked at creation

Enter currents and state of charge thresholds that are compatible with the manufacturer's limits: Fuzz calculates its setpoints from these values, it does not know the internal limits of the battery. The Modbus configuration is detailed in Modbus assets.

πŸ” Check and troubleshoot a battery​

The battery must be Online in Assets, with a state of charge consistent with the manufacturer's display. On the battery page, the real-time measurements card shows the power and the state of charge.

SymptomProbable causeSolution
Battery offlineAddress, unit ID, Modbus disabledSee Common Modbus problems
The battery does not follow the strategySet power unticked, remote control not allowed in the battery, state of charge outside the limitsTick the action; allow external control in the battery; check the SoC thresholds
Charge and discharge reversedSign convention of the model or wiringContact Fuzz support with the battery reference