☀️ Photovoltaic installations
Connecting the photovoltaic (PV) installation to Fuzz makes it possible to measure solar production, to charge vehicles on the surplus and, if the inverter allows it, to limit production when necessary. Fuzz communicates with the inverter or with the data manager that groups the inverters (Huawei Smartlogger, SMA Datamanager…). The full form is described in Add a photovoltaic installation.
✅ Prerequisites
| Item | Required |
|---|---|
| Asset | An inverter or data manager from the compatible list, using Modbus TCP, Modbus RTU or MQTT |
| Hosting mode | Modbus: Edge or Hybrid. MQTT: all modes |
| Role | Administrator or Operator of the site |
| Inverter setting | Modbus enabled on the inverter or data manager (often disabled at the factory); for production limiting, remote power control allowed in the inverter |
When several inverters are grouped by a data manager, preferably declare a single photovoltaic installation that queries the data manager.
📈 What Fuzz measures and controls on a PV installation
Measurements: Fuzz reads the power produced, the current per phase and the energy produced, depending on what the inverter model exposes. They appear in Assets (State tab, Photovoltaics filter), in the Energy flow diagram of the site Overview page (PHOTOVOLTAIC) and in the asset history.
Control: if the Set power (flexible asset) box is ticked in the Supported actions card (unticked by default), Fuzz can send a power setpoint to the inverter to limit production:
- to avoid exceeding the Maximum current (A) of a switchboard when production is too high;
- when the electricity price is negative, if the Negative price PV curtailment option is enabled at the Smart charging step of the site parameters (see Smart charging settings).
If the box is unticked, the installation is only measured: Fuzz never changes production. Solar surplus is also used to charge low-priority vehicles: see Charge vehicles on the solar surplus. Surplus charging also requires a main meter.
🖥️ Declare the installation in the Console
The form has six steps: Photovoltaic parameters, Photovoltaic protocol, Phase mapping, Console, Metrics, Monitoring.
| Field | Meaning | Default |
|---|---|---|
| Photovoltaic name | Name, unique on the site | — |
| Switchboard | Switchboard the installation feeds into | — |
| Meter | Dedicated meter, only if the inverter does not provide its own measurements | empty |
| Maximum current (A) | Maximum current of the installation per phase | 16 |
| Correction factor | Percentage of the measured production that Fuzz takes into account to calculate the available power: a safety margin because solar production varies quickly | 30 % |
| L1 / L2 / L3 Correction factor (%) | Same factor, phase by phase | 30 % |
| Protocol | Modbus or Mqtt, then Model | Modbus |
| Supported actions | Set power (flexible asset) | Unticked |
| Asset can be offline (Modbus configuration card) | Tick it: an inverter often switches off at night, which is not a fault | Unticked |
The Modbus configuration (IP address, port, unit ID, or RS485 bus) is detailed in Modbus assets.
🔍 Check and troubleshoot a PV installation
During the day, the installation must be Online in Assets with a power P (W) consistent with the sunshine. A power displayed as negative or reversed on a phase is corrected with Reverse current at the Phase mapping step.
| Symptom | Probable cause | Solution |
|---|---|---|
| Offline every night, needless alerts | Inverter switched off without production | Tick Asset can be offline |
| Offline during the day | Modbus disabled on the inverter, wrong address or unit ID | Enable Modbus TCP on the inverter; see Common Modbus problems |
| Production is never limited | Set power (flexible asset) unticked, or remote control refused by the inverter | Tick the action; allow power control in the inverter |
| Charge points do not charge on the surplus | No main meter, badge priorities | See Charge vehicles on the solar surplus |