βœ… Checklist before commissioning

A commissioning goes well when all the information is gathered before going on site. This checklist lists what to ask the customer, their electrician and their IT department, in the order the Console will need it. It follows the path described in Commissioning a site, step by step.


🏒 1. The customer and the site​

This information is used to create the customer company (Companies > Create customer company) then the site (Sites > Create site).

InformationConsole fieldNote
Customer company nameCompany nameExample: Nordhem
Company email and phoneEmail, Phone numberPhone in international format: +3242457692
VAT number, company numberVAT number, Company numberOptional
Company addressStreet name, Number, Box Number, Postal code, City, CountryCountry is Belgium by default
Site nameSite nameMust start with the company name: Nordhem Hognoul. See The site
On-site contactContact email, Contact phone numberThe person to notify for the site
Site address and GPS coordinatesAddress block, then Latitude and LongitudeThe Click to Fill in latitude and longitude coordinates based on address link calculates the coordinates from the address; if it fails (recent or poorly known address), read them off a map and enter them
EAN code of the connection point (Belgium)EAN18 digits, for example 541448912345678912; useful for Energy Units reports
Public access to the charge points (Belgium)Charge point accessPublic, Semi Public or Private (default); useful for Energy Units reports

πŸ–₯️ 2. The controller, the hosting mode and the licences​

InformationWhyWhere to get it
Hosting mode: Edge, Hybrid or CloudDetermines the hardware to install and the network to planSee Choose the hosting mode
Controller (Edge) or gateway (Hybrid) availableA site is attached to a free controller of the same modeDelivered by Fuzz after agreement; contact support@fuzz.energy
Serial number of the controllerTo choose in Fuzz Controller's serial numberMAC address of the eth0 port, on the label of the enclosure
Required licences: Timeseries Database (history), Monitoring & Alerting (alerts, reports), Energy Units Reports (Belgium)Without a licence, these menus do not appearAsk Fuzz to enable them before commissioning. See Licences

⚑ 3. The grid connection and tariffs​

InformationConsole fieldNote
Maximum connection power (kW)Maximum Power (kW) of the gridThe limit that smart charging will never let be exceeded. Without a main meter, enter the share reserved for charging. See Smart charging
Distribution system operator (DSO)Distribution System OperatorFluvius, RESA, ORES, Sibelga or Other
Peak / off-peak time rangesOff-peak scheduleSingle Rate, Dual Rate (10 PM-7 AM + weekends) by default, Dual Rate (9 PM-6 AM + weekends), Dual Rate (11 AM-5 PM + 10 PM-7 AM), Triple Rate / IMPACT
Connection levelElectrical connection levelLow voltage up to 56 kVA, above 56 kVA, Trans-LV, medium voltage, Trans-MV, high voltage
Capacity tariffCapacity tariffYes or no. Ticked, Fuzz measures and limits the site's quarter-hour peak. Also note, from the bills, the monthly peak and the annual peak of the last months: they are used to start the limit without waiting for a month of measurement. See Grid tariffs: capacity tariff
Buying and selling price formulasBuying price formula, Selling price formula (peak, off-peak, medium)According to the energy contract: X * Belpex + Y, X * Belix + Y or fixed price
VAT rate and deductible VATVAT rate (%), Deductible VAT rate (%)21% and 100% by default

πŸ‘‰ See: Grid tariffs


🌳 4. The electrical topology​

Smart charging only protects properly what it knows. Ask for the up-to-date single-line diagram and note:

  • the main low voltage switchboard and its rating per phase (A);
  • each sub-switchboard that supplies charge points or controlled assets, with its rating (A) and the switchboard that supplies it;
  • the existing meters or those to be installed, and the switchboard they measure; at a minimum, plan a meter on the main switchboard if you want solar surplus or to take the building's other consumption into account;
  • for each charge point, the switchboard that supplies it, the number of phases and the phase connection order (rotation).

πŸ‘‰ See: Electrical topology survey


πŸ”Œ 5. The list of assets​

For each asset, note:

AssetWhat to note
Charge pointMake, model, serial number, number of connectors, power and maximum current per connector (A), number of phases, accepted minimum current (often 6 or 7 A), support for OCPP 1.6J and OCPP smart charging, access to its configuration page (IP address, installer login provided by the manufacturer), EMI3 identifier if Energy Units reports are used
MeterMake, model, protocol (Modbus TCP, Modbus RTU or MQTT), maximum current (A), switchboard measured
Photovoltaic inverterMake, model, protocol, maximum current (A), peak power, controllable or not
BatteryMake, model, protocol, capacity (kWh), maximum charge and discharge currents (A), desired state of charge limits (%)
Fridge, other Modbus assetMake, model, protocol, Modbus register documentation

Communication data by protocol:

  • Modbus TCP: fixed IP address, port (502 by default), Modbus identifier (Unit ID).
  • Modbus RTU (RS485): Modbus identifier, speed (baud rate, 9600 to 115200, often 19200), parity, data bits, stop bits; all the assets on the same bus must have the same settings.
  • MQTT: the broker used and the topics published.
  • Asset web interface: IP address, HTTP or HTTPS protocol, port.

Check each model in Compatible hardware. A model that is not in the list requires Fuzz's opinion before ordering.


🌐 6. The IT network​

Send the page IT network to the customer's IT department and obtain:

  • a network socket for the controller, with outbound Internet access;
  • its IP address: fixed (DHCP reservation on the MAC address, or address entered in the installer menu) as soon as there are OCPP charge points on the local network;
  • the firewall openings towards the Fuzz servers;
  • fixed IP addresses for the Modbus TCP assets and for the assets whose web interface you want to open remotely;
  • for charge points connected through the Internet (Hybrid, Cloud, or exposed Edge site): their Internet access (site network or SIM card).

πŸͺͺ 7. Charging authorization, badges and CPO​

InformationNote
Authorization mode of each charge pointPlug & Charge (no badge), Local (whitelist badges), CPO, Local then CPO. See Charging authorization
List of badgesIdentifier (ID Tag), first name, last name, priority, active. A CSV file can be imported in one go (columns idTag, firstName, lastName, priority, active, priceModulationEnabled, priceHigh, priceLow, priceModulationDelaySec). See Badges (ID tags)
CPO, if anyCPO name, protocol (OCPP or REST), URL provided by the CPO, identifier of each charge point at the CPO (CPO Station ID), default badge to declare at the CPO
Desired priority rulesPriority badges or charge points, charging on solar surplus, modulation by price. See Smart charging

πŸ‘₯ 8. Users and alerts​

  • Customer users: name, first name, email and role of each person (Reporting for the site manager, IAM Administrator for the person who creates their colleagues' accounts, Read Only for viewing). See Users, groups and roles.
  • Alert recipients: email addresses, Telegram group or webhook URL, and the situations to report (charge point in fault, asset offline…). See Notification channels.
  • Your team's access: which groups in your company must have access to the customer (the Manage access step of company creation).

πŸ—’οΈ Checklist summary​

  • Customer company details and site name (starts with the company name)
  • Hosting mode chosen, controller or gateway available, serial number noted
  • Licences requested from Fuzz
  • Connection power (kW), DSO, tariff time ranges, price formulas
  • Single-line diagram, switchboard ratings, meters, charge point phases
  • List of assets with make, model, protocol and communication data
  • Network prerequisites sent and validated by the customer's IT
  • Authorization mode, list of badges, CPO data
  • Customer users and their roles, alert recipients